On 23 March, two tunnel boring machines — each weighing over 2,000...

They were meant to arrive in October 2024.
This thread, and the accompanying story, is about what held them up.
📷
The geology is mixed. The depth ranges from 25 to 65 metres. No machine built in India could do this job. It had to be imported from China.
Beijing's response: quietly delaying customs clearance for industrial equipment bound for India.
The TBMs were caught in that net. What followed was 18 months of escalating diplomatic effort.
Piyush Goyal confronted Germany's Vice Chancellor about it on a Delhi Metro train. The Prime Minister raised it directly with Xi Jinping at the SCO summit.
At 13.56 metres in diameter, it is the largest TBM ever deployed on Indian soil. Wide enough to carry both up and down rail tracks in a single tube.
For context: standard Indian metro TBMs are 6.6 metres. The Mumbai Coastal Road's Mavala, considered enormous at the time, was 12.19 metres.
Herrenknecht itself is investing ₹250 crore in a new large-diameter manufacturing plant in Chennai. The market signal is there.
--foreign exchange spent,
--a supply chain India doesn't control
The machine that reached Mumbai this week arrived late—and only after months of diplomacy.
The next fifteen years of tunnelling don't have to follow the same script.