The endgame for $YCA & their 21.68Mlb #uranium (not end of deficit)...

vs
Delays:
Phoenix=>8.4Mlb supply loss
Tumas=>3.6Mlb
Zuuvch Ovoo=>2x7Mlb
Arrow=>2x25Mlb
Mulga Rock
US producers slower ramp ups
🇰🇿lower prod than previously hoped
Reactor restarts & licence extension
🧵1/n

The utilities as global group are too late. They just don’t know it yet,bc they only look at their own needs
🇨🇳accelerating☢️reactor 🏗️,🇯🇵 restarting reactors & aiming to🏗️ new ones,🇺🇸 extends+restarts reactors
1/n
Me:Intermediaries will make $YCA takeover bid with backing of utilities & some producers
KAP UROY will possibly want YCA piece too to get lbs
But 1st awakening resulting in⬆️price will happen
2/n

Once stakeholders & investors will understand that $YCA takeover is the only temporary solution:
1/3
& they borrowed 200klb from BOE in 2024 bc they produced less than hoped
Total production of US miners (PEN UUUU URG EU UEC) didn’t even reach 1Mlb/y in2024 despite all their signed supply commitments towards clients
4/n
$YCA

& if you compare presentation of Encore Energy of 2y ago with the presentation today,you’ll notice they delayed uranium production too
No 5Mlb/y in 2028 anymore
$YCA $U.UN
Shirely Basin will be the same
5/n
$YCA

Promise 2022: 800klb produced from Lost Creek in 2024, add 1000klb from Shirely Basin in 2025
Reality: 266klb produced in 2024.
Shirely production start now in 2026
$YCA $U.UN
I remember Amir saying >3y ago that UEC needed sustained 80USD/lb (inflation escalated) to start producing
CCJ said the same back then
6/n
$YCA

Their total uranium production
2022: 0lb
2023: 0lb
2024: Christensen ISR mine restart in August => couple 10klb produced
2025: ?
Total US #uranium production Q4 2024 375klb & 310klb in Q1 2025🤣
Those utilities are now all of sudden uncovered
But Cameco, Orano & Kazatomprom are fully booked for 2026/2028
CCJ, Orano & KAP even need to buy in spot sometimes
7/n
$YCA

$YCA $U.UN
Bc this made/makes those #uranium producers net uranium BUYERS!
Which reduced the secondary supply to a very low level. Mathematically that secondary supply is now gone.
9/n
$YCA $U.UN

My detailed report (30 pages): “An important pivotal point has been reached. And the Uranium spotmarket is about to become much more tight”
See 30 pictures = 30 pages over a couple tweets.
$U.UN $YCA $URA $URNM $HURA $GCL #uranium
(1/6)
Confirmed in 2H 2024 by UxC with the picture below
With inventory X gone,the🌎structural primary supply deficit can’t be compensated anymore
10/n
#uranium
$YCA $U.UN

Surprise. During high season that followed uranium spotprice went⬆️
(1/3)
$U.UN
12/n
$YCA

$YCA $U.UN
13/n
$YCA

This alone would significantly delay the construction of the Patterson Lake South (Triple R) uranium mine (~9Mlb/y) & Arrow (Rook 1) uranium mine (~25Mlb/y) = several years of huge #uranium supply loss
This chart was before this requirement of unanimous approval
14/n
$YCA $U.UN

But NXE didn’t start construction yet & will probably not start in2026 too
Early 2026+4y = early 2030
End 2026-> early 2031
1/2
$YCA $U.UN
15/n
$YCA

If 2y delay = 2 x 3.6Mlb definitive uranium supply loss
$YCA $U.UN
16/n
$YCA

$YCA $U.UN
17/n
$YCA

$YCA $U.UN
18/n
$YCA

In 2024: Paladin Energy lowered their production estimates 2 times last 18months
But in 2022/2023 PDN promised a 6Mlb/y production by now= #uranium supply loss
$YCA $U.UN
19/n
$YCA

$YCA $U.UN